Bathhouse Renovation - July 16th, 2018 Update

An update on the Canyon Creek Bathhouse Renovation project was provided at the Canyon Creek Board of Directors meeting on July 16th, 2018.  The charts pertaining to renovation may be viewed here

When completed Spring 2018, Canyon Creek will have a completely refurbished facility that offers:

  • Family-friendly changing rooms;
  • Year-round toilet access for the adjacent courts, playground and park space;
  • Approximately 1000 sq ft covered patio space for picnics, parties or just comfortable shade.

Project Schedule as of August 9th, 2018

Project construction is scheduled to begin October 1st, 2018 pool and complete in April 2019.  See the following schedule graphic below.

2018-08-09 Remodeling Schedule.png

The architectural drawings and specifications were completed August 7th, 2019 and may be viewed below.


Page Revision History

  • Updated August 9th, 2018 by jmw with information from July 16th Board of Directors meeting and August 7th sealed permit drawings.